Assessment Year | 2007 |
---|---|
Principal Product | Ductile Iron Castings |
NAICS | 331511: Iron Foundries |
SIC | 3321: Gray and Ductile Iron Foundries |
Sales Range | $50 M to 100M |
# of Employees | 425 |
Plant Area |
273,000
ft2
|
Annual Production | 700,000
ton
|
Production Hrs. Annual | 60,000
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,033,892 | 30,940,093 |
kWh
|
$0.066 |
Electricity Demand | $851,029 | 94,898 |
kW-mo/yr
|
$8.97 |
Electricity Fees | $495 | - |
|
- |
Natural Gas | $891,846 | 110,298 |
MMBtu
|
$8.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $396,623 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $201,724 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $154,115 | $300,000 | - | - |
$154,115
-
MMBtu
|
|
02 | 2.2514: Cover open tanks | $115,389 | $140,000 | - | - |
$115,389
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $74,880 | $39,375 |
$58,827
894,840
kWh
|
$16,053
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $40,784 | $265,000 |
$40,784
620,424
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,455 | $6,300 |
$8,999
136,890
kWh
|
$2,456
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $396,623 | $750,675 |
$108,610
1,652,154
kWh
|
$18,509
-
kW-mo/yr
|
$269,504
-
MMBtu
|
||
TOTAL IMPLEMENTED | $201,724 | $185,675 |
$67,826
1,031,730
kWh
|
$18,509
-
kW-mo/yr
|
$115,389
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs