ITAC Assessment: UA0098
ITAC logo
ITAC Assessment: UA0098
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Tires
NAICS 326211: Tire Manufacturing (except Retreading)
SIC 3011: Tires and Inner Tubes
Sales Range $100
M
to 500
M
# of Employees 1,750
Plant Area 1,515,000
ft2
Annual Production 4,200,000
pieces
Production Hrs. Annual 8,600
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $10,000,000 163,934,426
kWh
Electricity Demand $828,144 194,400
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $218,698 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $132,802

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $55,414 $35,390 $45,032
738,223
kWh
$10,382
-
kW-mo/yr
02 2.4224: Upgrade controls on compressors $51,977 $20,000 $47,754
782,845
kWh
$4,223
-
kW-mo/yr
03 2.4239: Eliminate or reduce compressed air usage $25,411 $3,500 $25,207
413,226
kWh
$204
-
kW-mo/yr
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $69,733 $36,138 $69,733
1,143,160
kWh
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,024 $34,540 $7,024
115,150
kWh
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,139 $22,860 $9,139
149,824
kWh
-
TOTAL RECOMMENDED $218,698 $152,428 $203,889
3,342,428
kWh
$14,809
-
kW-mo/yr
TOTAL IMPLEMENTED $132,802 $58,890 $117,993
1,934,294
kWh
$14,809
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs