ITAC Assessment: NV0071
ITAC logo
ITAC Assessment: NV0071
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Beverages
NAICS
n/a
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 109,850
ft2
Annual Production 4,000,000
units
Production Hrs. Annual 5,720
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $217,127 4,229,191
kWh
Electricity Demand $2,267 298
kW-mo/yr
Natural Gas $35,842 6,891
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,950 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,664

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,634 $200 $1,634
31,946
kWh
- - -
02 2.7135: Install occupancy sensors $1,257 $227 $924
17,878
kWh
$333
-
kW-mo/yr
- -
03 2.7111: Reduce illumination to minimum necessary levels $2,001 $250 $1,544
28,722
kWh
$457
-
kW-mo/yr
- -
04 2.2511: Insulate bare equipment $7,692 $5,668 - - $7,692
-
MMBtu
-
05 2.4133: Use most efficient type of electric motors $1,337 $3,292 $1,303
25,498
kWh
$34
-
kW-mo/yr
- -
06 3.7221: Improve process control to prevent spills of material $1,029 $260 - - - $1,029
-
lb
TOTAL RECOMMENDED $14,950 $9,897 $5,405
104,044
kWh
$824
-
kW-mo/yr
$7,692
-
MMBtu
$1,029
-
lb
TOTAL IMPLEMENTED $12,664 $9,410 $4,481
86,166
kWh
$491
-
kW-mo/yr
$7,692
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs