ITAC Assessment: UA0097
ITAC logo
ITAC Assessment: UA0097
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Newspapers
NAICS 511110: Newspaper Publishers
SIC 2711: Newspapers: Publishing, or Publishing and Printing
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 96,000
ft2
Annual Production 63,000,000
pieces
Production Hrs. Annual 6,864
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $254,910 3,727,314
kWh
Electricity Fees $17,244 -
Natural Gas $36,447 2,930
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,817 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,219

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $11,720 $2,301 $7,231
105,717
kWh
$396 $4,093
-
MMBtu
02 2.7261: Install timers and/or thermostats $10,770 $3,452 $8,469
123,819
kWh
$534 $1,767
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $17,628 $18,309 $16,714
244,350
kWh
$914 -
04 2.7135: Install occupancy sensors $3,317 $299 $3,145
45,979
kWh
$172 -
05 2.7135: Install occupancy sensors $1,163 $1,646 $1,103
16,119
kWh
$60 -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,219 $2,500 $5,896
86,194
kWh
$323 -
TOTAL RECOMMENDED $50,817 $28,507 $42,558
622,178
kWh
$2,399 $5,860
-
MMBtu
TOTAL IMPLEMENTED $6,219 $2,500 $5,896
86,194
kWh
$323 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs