ITAC Assessment: MI0009
ITAC logo
ITAC Assessment: MI0009
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Sheet metal fabrication/precision machining
NAICS
n/a
SIC 3444: Sheet Metal Work
Sales Range $5
M
to 10
M
# of Employees 114
Plant Area 58,686
ft2
Annual Production 0
units
Production Hrs. Annual 5,148
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $41,769 771,600
kWh
Electricity Demand $20,316 2,298
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $77,475 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Primary Product Savings
01 2.7144: Install spectral reflectors / delamp $14,580 $5,000 - $14,580
02 2.7221: Lower temperature during the winter season and vice-versa $2,327 $12 $2,327
13,058
kWh
-
03 2.7221: Lower temperature during the winter season and vice-versa $6,745 $12 $6,745
69,682
kWh
-
04 4.122: Develop standard procedures to improve internal yields $43,740 $2,550 - $43,740
05 2.7447: Install vinyl strip / high speed / air curtain doors $10,083 $1,102 $10,083
190,246
kWh
-
TOTAL RECOMMENDED $77,475 $8,676 $19,155
272,986
kWh
$58,320
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs