Assessment Year | 2012 |
---|---|
Principal Product | Tires |
NAICS | 326211: Tire Manufacturing (except Retreading) |
SIC | 3011: Tires and Inner Tubes |
Sales Range | greater than $500 M |
# of Employees | 1,800 |
Plant Area |
1,600,000
ft2
|
Annual Production | 14,000,000
pieces
|
Production Hrs. Annual | 8,664
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $5,422,730 | 135,568,238 |
kWh
|
$0.040 |
Electricity Demand | $4,815,421 | 399,948 |
kW-mo/yr
|
$12.04 |
Natural Gas | $1,761,849 | 537,149 |
MMBtu
|
$3.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,811,885 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $374,463 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust | $6,264,801 | $14,443,176 |
$5,422,729
135,568,238
kWh
|
$4,815,374
-
kW-mo/yr
|
$1,761,849
-
MMBtu
|
$(-5,735,151.0) | |
02 | 2.2136: Install / repair insulation on steam lines | $164,656 | $57,024 | - | - |
$164,656
-
MMBtu
|
- | |
03 | 2.3321: Use steam pressure reduction to generate power | $86,957 | $214,808 |
$67,677
1,691,920
kWh
|
$27,740
-
kW-mo/yr
|
- | $(-8,460.0) | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,936 | $7,682 |
$7,745
193,623
kWh
|
$3,191
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $151,364 | $35,390 |
$107,178
2,679,440
kWh
|
$44,186
-
kW-mo/yr
|
- | - | |
06 | 2.4226: Use / purchase optimum sized compressor | $146,229 | $68,100 |
$103,297
2,582,432
kWh
|
$42,932
-
kW-mo/yr
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $58,443 | $1,920 |
$40,701
1,017,514
kWh
|
$17,742
-
kW-mo/yr
|
- | - | |
08 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $48,968 | $131,587 |
$31,365
784,133
kWh
|
$17,603
-
kW-mo/yr
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $349,571 | $177,363 |
$250,120
6,253,005
kWh
|
$99,451
-
kW-mo/yr
|
- | - | |
10 | 2.7273: Install desiccant humidity control system | $529,960 | $400,000 |
$560,631
14,015,775
kWh
|
- |
$(-30,671.0)
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $7,811,885 | $15,537,050 |
$6,591,443
164,786,080
kWh
|
$5,068,219
-
kW-mo/yr
|
$1,895,834
-
MMBtu
|
$(-5,743,611.0) | ||
TOTAL IMPLEMENTED | $374,463 | $94,334 |
$147,879
3,696,954
kWh
|
$61,928
-
kW-mo/yr
|
$164,656
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs