| Assessment Year | 2010 |
|---|---|
| Principal Product | forklift component assemblies |
| NAICS | 333924: Industrial Truck, Tractor, Trailer, and Stacker Machinery Manufacturing |
| SIC | 3537: Industrial Trucks, Tractors, Trailers, and Stackers |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
300,000
ft2
|
| Annual Production | 135,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,419,389 | 23,076,000 |
kWh
|
$0.062 |
| Electricity Demand | $200,362 | 48,813 |
kW-mo/yr
|
$4.10 |
| Electricity Fees | $24,000 | - |
|
- |
| Natural Gas | $954,251 | 38,404 |
MMBtu
|
$24.85 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $203,508 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,382 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $31,442 | $1,000 |
$25,860
420,415
kWh
|
$5,582
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,010 | $7,000 |
$10,343
168,155
kWh
|
$667
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $86,265 | $71,625 |
$79,040
1,284,987
kWh
|
$7,225
-
kW-mo/yr
|
- | |
| 04 | 2.7134: Use photocell controls | $2,443 | $1,893 |
$2,443
39,712
kWh
|
- | - | |
| 05 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $42,638 | $40,400 |
$40,678
656,104
kWh
|
$1,960
-
kW-mo/yr
|
- | |
| 06 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $25,338 | $6,850 |
$21,472
346,332
kWh
|
$3,866
-
kW-mo/yr
|
- | |
| 07 | 2.7261: Install timers and/or thermostats | $4,372 | $3,230 |
$2,506
40,416
kWh
|
- |
$1,866
-
MMBtu
|
|
| TOTAL RECOMMENDED | $203,508 | $131,998 |
$182,342
2,956,121
kWh
|
$19,300
-
kW-mo/yr
|
$1,866
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $15,382 | $10,230 |
$12,849
208,571
kWh
|
$667
-
kW-mo/yr
|
$1,866
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs