Assessment Year | 2010 |
---|---|
Principal Product | Parts for military tracked vehicles |
NAICS | 336992: Military Armored Vehicle, Tank, and Tank Component Manufacturing |
SIC | 3711: Motor Vehicles and Passenger Car Bodies |
Sales Range | $50 M to 100M |
# of Employees | 350 |
Plant Area |
280,000
ft2
|
Annual Production | 485,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,759,622 | 24,541,634 |
kWh
|
$0.072 |
Electricity Fees | $(-36,372.0) | - |
|
- |
Natural Gas | $951,340 | 84,235 |
MMBtu
|
$11.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $400,890 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $360,880 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $55,100 | $119,700 |
$55,100
784,685
kWh
|
- | |
02 | 2.7135: Install occupancy sensors | $2,630 | $380 |
$2,630
37,465
kWh
|
- | |
03 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $5,320 | $2,520 | - |
$5,320
-
MMBtu
|
|
04 | 2.4323: Use optimum size and capacity equipment | $216,130 | - | - |
$216,130
-
MMBtu
|
|
05 | 2.1113: Reduce combustion air flow to optimum | $76,495 | - | - |
$76,495
-
MMBtu
|
|
06 | 2.2425: Use flue gases to heat process or service water | $21,020 | $19,015 | - |
$21,020
-
MMBtu
|
|
07 | 2.2511: Insulate bare equipment | $1,020 | $2,450 | - |
$1,020
-
MMBtu
|
|
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,050 | $2 |
$1,050
14,890
kWh
|
- | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $13,310 | $22,000 |
$13,310
189,570
kWh
|
- | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,050 | $7 |
$3,050
43,470
kWh
|
- | |
11 | 2.7261: Install timers and/or thermostats | $5,765 | $675 |
$5,765
88,935
kWh
|
- | |
TOTAL RECOMMENDED | $400,890 | $166,748 |
$80,905
1,159,015
kWh
|
$319,985
-
MMBtu
|
||
TOTAL IMPLEMENTED | $360,880 | $125,347 |
$61,915
888,510
kWh
|
$298,965
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs