ITAC Assessment: UA0033
ITAC logo
ITAC Assessment: UA0033
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Asphalt Mix
NAICS 327390: Other Concrete Product Manufacturing
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $5
M
to 10
M
# of Employees 30
Plant Area 150,000
ft2
Annual Production 350,000
ton
Production Hrs. Annual 2,500
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $609,636 4,942,750
kWh
Fuel Oil #6 $900,000 68,500
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $159,395 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #6 Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $970 $700 $970
7,162
kWh
-
02 2.2437: Recover waste heat from equipment $96,325 $7,930 - $96,325
-
MMBtu
03 2.2511: Insulate bare equipment $570 $2,548 - $570
-
MMBtu
04 2.1113: Reduce combustion air flow to optimum $61,530 $16,083 $23,880
176,243
kWh
$37,650
-
MMBtu
TOTAL RECOMMENDED $159,395 $27,261 $24,850
183,405
kWh
$134,545
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs