Assessment Year | 2009 |
---|---|
Principal Product | Asphalt Mix |
NAICS | 327390: Other Concrete Product Manufacturing |
SIC | 2951: Asphalt Paving Mixtures and Blocks |
Sales Range | $5 M to 10M |
# of Employees | 30 |
Plant Area |
150,000
ft2
|
Annual Production | 350,000
ton
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $609,636 | 4,942,750 |
kWh
|
$0.12 |
Fuel Oil #6 | $900,000 | 68,500 |
MMBtu
|
$13.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $159,395 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #6 Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $970 | $700 |
$970
7,162
kWh
|
- | |
02 | 2.2437: Recover waste heat from equipment | $96,325 | $7,930 | - |
$96,325
-
MMBtu
|
|
03 | 2.2511: Insulate bare equipment | $570 | $2,548 | - |
$570
-
MMBtu
|
|
04 | 2.1113: Reduce combustion air flow to optimum | $61,530 | $16,083 |
$23,880
176,243
kWh
|
$37,650
-
MMBtu
|
|
TOTAL RECOMMENDED | $159,395 | $27,261 |
$24,850
183,405
kWh
|
$134,545
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs