ITAC Assessment: UA0015
ITAC logo
ITAC Assessment: UA0015
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Zinc batteries
NAICS 335912: Primary Battery Manufacturing
SIC 3692: Primary Batteries, Dry and Wet
Sales Range $1
M
to 5
M
# of Employees 35
Plant Area 30,000
ft2
Annual Production 8,800
pieces
Production Hrs. Annual 2,040
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,575 610,000
kWh
Electricity Demand $10,646 2,475
kW-mo/yr
Electricity Fees $648 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,931 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,777

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,437 $20,527 $3,522
37,284
kWh
$915
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $6,846 $35,708 $5,435
57,360
kWh
$1,411
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $871 $5,926 $693
7,313
kWh
$178
-
kW-mo/yr
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $204 - $204
2,239
kWh
- -
05 2.7261: Install timers and/or thermostats $7,573 $823 $2,473
26,110
kWh
- $5,100
TOTAL RECOMMENDED $19,931 $62,984 $12,327
130,306
kWh
$2,504
-
kW-mo/yr
$5,100
TOTAL IMPLEMENTED $7,777 $823 $2,677
28,349
kWh
- $5,100
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs