ITAC Assessment: TT0353
ITAC logo
ITAC Assessment: TT0353
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Galvanizing Steel
NAICS 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 54,000
ft2
Annual Production 50,000,000
lb
Production Hrs. Annual 7,488
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $160,493 1,768,845
kWh
Electricity Demand $42,976 4,893
kW-mo/yr
Electricity Fees $10,083 -
Natural Gas $599,096 87,175
MMBtu
Waste Disposal Costs
Water Usage $13,128 3,642
Tgal
Water Disposal $3,992 495
Tgal
TOTAL YEARLY COSTS $829,768
RECOMMENDED SAVINGS* $612,267 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $7,030 $70 - - $7,030 - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $11,064 $1,240 $10,923
120,388
kWh
$141
-
kW-mo/yr
- - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,960 $300 $1,960
21,785
kWh
- - - -
04 2.2511: Insulate bare equipment $3,727 $2,493 - - - $3,727
-
MMBtu
-
05 2.1224: Replace boiler $480,000 $152,000 - - - - $480,000
06 2.2424: Use heat in flue gases to preheat products or materials $71,592 $80,000 - - - $71,592
-
MMBtu
-
07 2.7135: Install occupancy sensors $2,806 $4,350 $2,806
30,925
kWh
- - - -
08 2.3212: Optimize plant power factor $3,128 $9,435 - - $3,128 - -
09 2.2414: Use waste heat from hot flue gases to preheat $28,283 $60,000 - - - $28,283
-
MMBtu
-
10 2.4224: Upgrade controls on compressors $2,152 $5,000 $2,152
23,730
kWh
- - - -
11 2.4224: Upgrade controls on compressors $525 $1,520 $525
5,829
kWh
- - - -
TOTAL RECOMMENDED $612,267 $316,408 $18,365
202,658
kWh
$141
-
kW-mo/yr
$10,158 $103,602
-
MMBtu
$480,000
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs