| Assessment Year | 2024 |
|---|---|
| Principal Product | Bottled Water |
| NAICS | 312112: Bottled Water Manufacturing |
| SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
| Sales Range | $100 M to 500M |
| # of Employees | 71 |
| Plant Area |
554,040
ft2
|
| Annual Production | 1,650,755,184
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $2,217,804 | 32,002,800 |
kWh
|
$0.069 | |
| Electricity Demand | $816,582 | 56,168 |
kW-mo/yr
|
$14.54 | |
| Natural Gas | $65,264 | 9,111 |
MMBtu
|
$7.16 | |
| Waste Disposal Costs | |||||
| Water Usage | $905,317 | 249,533 |
Tgal
|
$3.63 | |
| Water Disposal | $240,422 | 81,054 |
Tgal
|
$2.97 | |
| TOTAL YEARLY COSTS | $4,245,389 | ||||
| RECOMMENDED SAVINGS* | $591,559 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $51,625 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $519,539 | $7,626,292 |
$519,539
7,496,959
kWh
|
- | - | - | - | - | |
| 02 | 2.4224: Upgrade controls on compressors | $25,497 | $30,000 |
$25,497
367,920
kWh
|
- | - | - | - | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $17,101 | $94 |
$13,280
191,632
kWh
|
$3,821
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,027 | $65,640 |
$7,006
101,099
kWh
|
$2,021
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,815 | $1,500 |
$6,071
87,600
kWh
|
$1,744
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.2441: Preheat boiler makeup water with waste process heat | $5,885 | $12,180 |
$792
11,435
kWh
|
- |
$5,093
-
MMBtu
|
- | - | - | |
| 07 | 3.4114: Replace city water with recycled water via cooling tower | $4,912 | $15,000 | - | - | - |
$4,353
-
Tgal
|
$3,559
-
Tgal
|
$(-3,000.0) | |
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,783 | $460 |
$693
10,000
kWh
|
$1,090
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $591,559 | $7,751,166 |
$572,878
8,266,645
kWh
|
$8,676
-
kW-mo/yr
|
$5,093
-
MMBtu
|
$4,353
-
Tgal
|
$3,559
-
Tgal
|
$(-3,000.0) | ||
| TOTAL IMPLEMENTED | $51,625 | $95,734 |
$45,783
660,651
kWh
|
$5,842
-
kW-mo/yr
|
- | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs