| Assessment Year | 2023 |
|---|---|
| Principal Product | Light-Duty Water Heaters |
| NAICS | 335228: Other Major Household Appliance Manufacturing |
| SIC | 3639: Household Appliances, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 988 |
| Plant Area |
539,000
ft2
|
| Annual Production | 1,612,000
units
|
| Production Hrs. Annual | 3,968
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,282,456 | 20,783,949 |
kWh
|
$0.062 | |
| Electricity Demand | $651,783 | 45,853 |
kW-mo/yr
|
$14.21 | |
| Natural Gas | $1,466,581 | 247,651 |
MMBtu
|
$5.92 | |
| Waste Disposal Costs | |||||
| Water Usage | $91,006 | 8,584 |
Tgal
|
$10.60 | |
| TOTAL YEARLY COSTS | $3,491,826 | ||||
| RECOMMENDED SAVINGS* | $93,192 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $28,864 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Usage Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $49,703 | $203,650 |
$49,703
805,540
kWh
|
- | - | - | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $13,890 | $1,250 |
$13,890
225,124
kWh
|
- | - | - | |
| 03 | 2.7135: Install occupancy sensors | $11,161 | $14,500 |
$11,161
180,900
kWh
|
- | - | - | |
| 04 | 2.3212: Optimize plant power factor | $8,533 | $20,000 | - | - | $8,533 | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,428 | $1,950 |
$5,428
87,970
kWh
|
- | - | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,512 | $6,000 |
$1,553
25,178
kWh
|
$959
-
kW-mo/yr
|
- | - | |
| 07 | 3.5132: Reuse rich white water in other applications | $1,230 | $1,820 | - | - | - |
$1,230
-
Tgal
|
|
| 08 | 2.6218: Turn off equipment when not in use | $735 | $750 |
$621
10,058
kWh
|
$114
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $93,192 | $249,920 |
$82,356
1,334,770
kWh
|
$1,073
-
kW-mo/yr
|
$8,533 |
$1,230
-
Tgal
|
||
| TOTAL IMPLEMENTED | $28,864 | $44,270 |
$18,142
294,048
kWh
|
$959
-
kW-mo/yr
|
$8,533 |
$1,230
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs