Assessment Year | 1999 |
---|---|
Principal Product | Fiber batting for furniture |
NAICS |
n/a
|
SIC | 2290: |
Sales Range | $10 M to 50M |
# of Employees | 82 |
Plant Area |
200,000
ft2
|
Annual Production | 15,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $65,800 | 2,231,243 |
kWh
|
$0.029 |
Electricity Demand | $59,403 | 6,306 |
kW-mo/yr
|
$9.42 |
Electricity Fees | $720 | - |
|
- |
Natural Gas | $62,190 | 12,274 |
MMBtu
|
$5.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $143,859 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $45,360 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | By-product Production Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $384 | $120 |
$256
8,206
kWh
|
$128
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | - | |
02 | 2.7135: Install occupancy sensors | $235 | $250 |
$235
7,913
kWh
|
- | - | - | - | - | - | - | - | - | - | |
03 | 2.2437: Recover waste heat from equipment | $3,937 | $1,000 | - | - |
$3,937
-
MMBtu
|
- | - | - | - | - | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $972 | $907 |
$496
16,706
kWh
|
$476
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | - | |
05 | 2.4226: Use / purchase optimum sized compressor | $12,762 | - |
$7,788
264,068
kWh
|
$4,974
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | - | |
06 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $5,335 | $20,780 | - | - |
$5,335
-
MMBtu
|
- | - | - | - | - | - | - | - | |
07 | 2.7313: Recycle air for heating, ventilation and air conditioning | $5,794 | $2,500 | - | - |
$5,794
-
MMBtu
|
- | - | - | - | - | - | - | - | |
08 | 3.1192: Reduce scrap production | $2,360 | $4,100 | - | - | - | - |
$120
-
lb
|
- | - | $2,240 | - | - | - | |
09 | 4.521: Clear and rent existing space | $26,000 | $640 | - | - | - | - | - | - | - | - | - | $26,000 | - | |
10 | 4.423: Move product using mechanical means | $3,600 | $500 | - | - | - | - | - | $3,600 | - | - | - | - | - | |
11 | 4.611: Begin a practice of predictive / preventative maintenance | $680 | $1,000 | - | - | - | - | - | $(-500.0) | $1,430 | - | $(-250.0) | - | - | |
12 | 4.424: Improve space comfort conditioning | $81,800 | $13,500 | - | - | - |
$(-100.0)
-
Tgal
|
- | - | - | - | - | - | $81,900 | |
TOTAL RECOMMENDED | $143,859 | $45,297 |
$8,775
296,893
kWh
|
$5,578
-
kW-mo/yr
|
$15,066
-
MMBtu
|
$(-100.0)
-
Tgal
|
$120
-
lb
|
$3,100 | $1,430 | $2,240 | $(-250.0) | $26,000 | $81,900 | ||
TOTAL IMPLEMENTED | $45,360 | $30,797 |
$987
32,825
kWh
|
$604
-
kW-mo/yr
|
$11,129
-
MMBtu
|
- |
$120
-
lb
|
$3,100 | $1,430 | $2,240 | $(-250.0) | $26,000 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | By-product Production Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs