ITAC Assessment: TT0289
ITAC logo
ITAC Assessment: TT0289
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Plastic Caps
NAICS 325991: Custom Compounding of Purchased Resins
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 100
Plant Area 135,000
ft2
Annual Production 3,800,000,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,324,125 26,866,000
kWh
Electricity Demand $466,382 72,478
kW-mo/yr
Natural Gas $23,566 2,623
MMBtu
Waste Disposal Costs
Water Usage $18,600 8,044
Tgal
TOTAL YEARLY COSTS $1,832,673
RECOMMENDED SAVINGS* $90,654 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $83,136

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,836 $40 $2,406
48,793
kWh
$430
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,365 $1,405 $5,281
107,111
kWh
$85
-
kW-mo/yr
-
03 2.6212: Turn off equipment during breaks, reduce operating time $5,799 $2,000 $5,799
117,629
kWh
- -
04 2.2437: Recover waste heat from equipment $13,798 $13,000 - - $13,798
-
MMBtu
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,719 $1,609 $1,101
22,338
kWh
$618
-
kW-mo/yr
-
06 2.4226: Use / purchase optimum sized compressor $61,137 $119,000 $51,798
1,050,661
kWh
$9,340
-
kW-mo/yr
-
TOTAL RECOMMENDED $90,654 $137,054 $66,384
1,346,533
kWh
$10,473
-
kW-mo/yr
$13,798
-
MMBtu
TOTAL IMPLEMENTED $83,136 $133,445 $59,484
1,206,565
kWh
$9,855
-
kW-mo/yr
$13,798
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs