ITAC Assessment: MI0068
ITAC logo
ITAC Assessment: MI0068
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Aluminum and plastic parts
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 35
Plant Area 43,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,990
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Demand $31,442 654,960
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,572 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $291

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 4.323: Optimize lot sizes to reduce inventory carrying costs $2,625 $80 - $2,625
02 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $1,426 $285 $1,426
20,346
kWh
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $131 $155 $131
1,422
kWh
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $291 $29 $291
4,157
kWh
-
05 2.6218: Turn off equipment when not in use $8,099 $169 $8,099
115,696
kWh
-
TOTAL RECOMMENDED $12,572 $718 $9,947
141,621
kWh
$2,625
TOTAL IMPLEMENTED $291 $29 $291
4,157
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs