ITAC Assessment: TT0288
ITAC logo
ITAC Assessment: TT0288
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Wood Perservatives
NAICS 325320: Pesticide and Other Agricultural Chemical Manufacturing
SIC 2879: Pesticides and Agricultural Chemicals, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 105
Plant Area 580,000
ft2
Annual Production 156,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $299,278 4,395,600
kWh
Electricity Demand $132,611 9,615
kW-mo/yr
Natural Gas $108,115 18,866
MMBtu
LPG $16,650 453
MMBtu
Waste Disposal Costs
Water Usage $34,633 11,186
Tgal
Water Disposal $37,164 11,186
Tgal
TOTAL YEARLY COSTS $628,451
RECOMMENDED SAVINGS* $118,544 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $76,327

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Water Disposal Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $33,933 $15,640 $26,564
390,082
kWh
$7,369
-
kW-mo/yr
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $28,247 $63,960 $21,076
309,491
kWh
$7,171
-
kW-mo/yr
- - - -
03 2.1321: Replace fossil fuel equipment with electrical equipment $17,505 - $(-1,845.0)
(-27,093)
kWh
- $16,650
-
MMBtu
- - $2,700
04 3.4155: Meter waste water $15,491 $1,100 - - - $15,491
-
Tgal
- -
05 2.4133: Use most efficient type of electric motors $11,036 $28,000 $1,236
18,149
kWh
- - - $9,800 -
06 2.4239: Eliminate or reduce compressed air usage $4,257 $14,220 $4,257
62,500
kWh
- - - - -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,111 $3,350 $2,350
34,536
kWh
$761
-
kW-mo/yr
- - - -
08 2.4151: Develop a repair/replace policy $2,464 $7,410 $2,370
35,328
kWh
$94
-
kW-mo/yr
- - - -
09 2.4231: Reduce the pressure of compressed air to the minimum required $1,975 $63 $1,975
28,999
kWh
- - - - -
10 2.4237: Substitute compressed air cooling with water or air cooling $525 $1,600 $525
7,713
kWh
- - - - -
TOTAL RECOMMENDED $118,544 $135,343 $58,508
859,705
kWh
$15,395
-
kW-mo/yr
$16,650
-
MMBtu
$15,491
-
Tgal
$9,800 $2,700
TOTAL IMPLEMENTED $76,327 $110,950 $51,226
752,258
kWh
$15,301
-
kW-mo/yr
- - $9,800 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Water Disposal Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs