| Assessment Year | 2022 |
|---|---|
| Principal Product | Yeast |
| NAICS | 311999: All Other Miscellaneous Food Manufacturing |
| SIC | 2099: Food Preparations, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 58 |
| Plant Area |
66,828
ft2
|
| Annual Production | 94,267,981
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,556,196 | 25,511,000 |
kWh
|
$0.061 | |
| Electricity Demand | $611,820 | 51,565 |
kW-mo/yr
|
$11.87 | |
| Natural Gas | $390,272 | 84,087 |
MMBtu
|
$4.64 | |
| Waste Disposal Costs | |||||
| Water Usage | $149,909 | 89,953 |
Tgal
|
$1.67 | |
| Water Disposal | $1,840,081 | 192,091 |
Tgal
|
$9.58 | |
| TOTAL YEARLY COSTS | $4,548,278 | ||||
| RECOMMENDED SAVINGS* | $1,422,830 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $1,323,104 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $816,618 | $2,873,364 |
$683,845
11,210,566
kWh
|
$173,597
-
kW-mo/yr
|
$43,477
-
MMBtu
|
$(-84,301.0) | |
| 02 | 2.2437: Recover waste heat from equipment | $360,908 | $51,360 |
$263,271
4,315,924
kWh
|
- |
$97,637
-
MMBtu
|
- | |
| 03 | 2.2437: Recover waste heat from equipment | $99,184 | $280,000 |
$78,754
1,291,052
kWh
|
- |
$20,430
-
MMBtu
|
- | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $48,725 | $152,000 |
$48,725
798,782
kWh
|
- | - | - | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $42,363 | $21,260 |
$42,363
694,483
kWh
|
- | - | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $41,290 | $58,960 |
$41,290
676,887
kWh
|
- | - | - | |
| 07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,200 | $15,000 |
$10,424
170,895
kWh
|
$2,776
-
kW-mo/yr
|
- | - | |
| 08 | 2.4237: Substitute compressed air cooling with water or air cooling | $542 | $1,120 |
$542
8,971
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $1,422,830 | $3,453,064 |
$1,169,214
19,167,560
kWh
|
$176,373
-
kW-mo/yr
|
$161,544
-
MMBtu
|
$(-84,301.0) | ||
| TOTAL IMPLEMENTED | $1,323,104 | $3,171,944 |
$1,089,918
17,867,537
kWh
|
$176,373
-
kW-mo/yr
|
$141,114
-
MMBtu
|
$(-84,301.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs