ITAC Assessment: TT0276
ITAC logo
ITAC Assessment: TT0276
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Fluid Management Systems for Small Trucks and SUVs
NAICS 332912: Fluid Power Valve and Hose Fitting Manufacturing
SIC 3492: Fluid Power Valves and Hose Fittings
Sales Range $50
M
to 100
M
# of Employees 500
Plant Area 173,475
ft2
Annual Production 1,246,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $672,168 9,536,083
kWh
Electricity Demand $296,540 19,813
kW-mo/yr
Electricity Fees $16,112 -
Natural Gas $45,339 4,779
MMBtu
Waste Disposal Costs
Water Usage $60,458 18,973
Tgal
Water Disposal $45,995 18,973
Tgal
TOTAL YEARLY COSTS $1,136,612
RECOMMENDED SAVINGS* $332,375 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $63,054

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 4.212: Adopt in-house material generation $42,153 $40,000 $(-1,138.0)
(-15,680)
kWh
$(-241.0)
-
kW-mo/yr
- - - $43,532 -
02 2.9114: Use solar heat to make electricty $125,911 $145,300 $42,138
583,546
kWh
$83,773
-
kW-mo/yr
- - - - -
03 2.2437: Recover waste heat from equipment $37,334 $25,000 - - - $37,334
-
MMBtu
- - -
04 3.6112: Use filter and drying oven to reduce sludge volume $35,279 $40,000 - - - $(-2,221.0)
-
MMBtu
$(-3,500.0)
-
Tgal
- $41,000
05 2.6218: Turn off equipment when not in use $22,303 $60 - - - $22,303
-
MMBtu
- - -
06 2.3212: Optimize plant power factor $16,112 $15,000 - - $16,112 - - - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $18,657 $3,175 $18,657
255,838
kWh
- - - - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $15,344 $24,750 $11,614
158,382
kWh
$3,730
-
kW-mo/yr
- - - - -
09 4.632: Change operating conditions $6,750 $2,000 - $6,750
-
kW-mo/yr
- - - - -
10 2.4231: Reduce the pressure of compressed air to the minimum required $5,766 $40 $5,766
78,489
kWh
- - - - - -
11 2.4221: Install compressor air intakes in coolest locations $4,311 $2,240 $3,078
42,619
kWh
$1,233
-
kW-mo/yr
- - - - -
12 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,455 $6,840 $2,455
34,824
kWh
- - - - - -
TOTAL RECOMMENDED $332,375 $304,405 $82,570
1,138,018
kWh
$95,245
-
kW-mo/yr
$16,112 $57,416
-
MMBtu
$(-3,500.0)
-
Tgal
$43,532 $41,000
TOTAL IMPLEMENTED $63,054 $29,985 $30,271
414,220
kWh
$10,480
-
kW-mo/yr
- $22,303
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs