Assessment Year | 2021 |
---|---|
Principal Product | Wire and Cable |
NAICS | 335921: Fiber Optic Cable Manufacturing |
SIC | 3357: Drawing and Insulating of Nonferrous Wire |
Sales Range | $50 M to 100M |
# of Employees | 109 |
Plant Area |
182,859
ft2
|
Annual Production | 421,000
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $626,303 | 10,069,880 |
kWh
|
$0.062 | |
Electricity Demand | $241,357 | 21,268 |
kW-mo/yr
|
$11.35 | |
Natural Gas | $9,812 | 1,328 |
MMBtu
|
$7.39 | |
Waste Disposal Costs | |||||
Water Usage | $9,597 | 38,656 |
Tgal
|
$0.25 | |
Water Disposal | $22,620 | 38,656 |
Tgal
|
$0.59 | |
TOTAL YEARLY COSTS | $909,689 | ||||
RECOMMENDED SAVINGS* | $319,413 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $269,726 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.7425: Clean or color roof to reduce solar load | $188,912 | $733,702 |
$51,499
827,960
kWh
|
$269
-
kW-mo/yr
|
$137,144 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $49,358 | $3,200 |
$36,163
581,400
kWh
|
$13,195
-
kW-mo/yr
|
- | |
03 | 2.7241: Install outside air damper / economizer on hvac unit | $30,912 | $38,200 |
$30,912
496,973
kWh
|
- | - | |
04 | 2.6218: Turn off equipment when not in use | $26,082 | $700 |
$26,082
419,328
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $9,133 | $3,000 |
$8,669
139,370
kWh
|
$464
-
kW-mo/yr
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,718 | $15,000 |
$6,718
108,006
kWh
|
- | - | |
07 | 2.4226: Use / purchase optimum sized compressor | $5,374 | - |
$4,250
68,550
kWh
|
$1,124
-
kW-mo/yr
|
- | |
08 | 2.7224: Reduce space conditioning during non-working hours | $2,221 | $9,600 |
$2,221
35,703
kWh
|
- | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $703 | $850 |
$515
8,280
kWh
|
$188
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $319,413 | $804,252 |
$167,029
2,685,570
kWh
|
$15,240
-
kW-mo/yr
|
$137,144 | ||
TOTAL IMPLEMENTED | $269,726 | $737,602 |
$117,994
1,897,238
kWh
|
$14,588
-
kW-mo/yr
|
$137,144 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs