ITAC Assessment: TT0258
ITAC logo
ITAC Assessment: TT0258
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Engineered Plastics
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 207,000
ft2
Annual Production 216,000,000
lb
Production Hrs. Annual 8,640
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,500,045 27,075,445
kWh
Electricity Demand $932,575 151,845
kW-mo/yr
Natural Gas $372,950 47,974
MMBtu
Waste Disposal Costs
Water Usage $59,676 15,622
Tgal
Water Disposal $81,078 15,622
Tgal
TOTAL YEARLY COSTS $2,946,324
RECOMMENDED SAVINGS* $93,087 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Ancillary Material Cost Savings
01 3.4114: Replace city water with recycled water via cooling tower $65,709 $230,400 $(-958.0)
(-17,297)
kWh
- - $36,168
-
Tgal
$49,139
-
Tgal
$(-18,640.0)
02 2.2414: Use waste heat from hot flue gases to preheat $10,627 $25,000 - - $10,627
-
MMBtu
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $7,751 $37,500 $7,751
139,903
kWh
- - - - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,652 $4,000 $3,170
57,229
kWh
$482
-
kW-mo/yr
- - - -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,092 $10,000 $2,092
37,764
kWh
- - - - -
06 2.1243: Use heat from boiler blowdown to preheat boiler feed water $1,703 $7,500 - - $1,703
-
MMBtu
- - -
07 2.6124: Establish equipment maintenance schedule $1,108 $5,000 $1,108
20,007
kWh
- - - - -
08 2.4151: Develop a repair/replace policy $445 - $(-1,925.0)
(-34,744)
kWh
$(-553.0)
-
kW-mo/yr
- - - $2,923
TOTAL RECOMMENDED $93,087 $319,400 $11,238
202,862
kWh
$(-71.5)
-
kW-mo/yr
$12,330
-
MMBtu
$36,168
-
Tgal
$49,139
-
Tgal
$(-15,717.0)
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs