ITAC Assessment: ST0025
ITAC logo
ITAC Assessment: ST0025
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product BATH ACCESSORIES
NAICS
n/a
SIC 2392: House furnishing, Except Curtains and Draperies
Sales Range $1
M
to 5
M
# of Employees 220
Plant Area
n/a
Annual Production 2,500,000
pieces
Production Hrs. Annual 2,040
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $176,681 939,625
kWh
Natural Gas $289 28
MMBtu
Fuel Oil #2 $28,130 4,410
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $104,187 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $51,769

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,196 $216 $7,196
38,394
kWh
- -
02 2.2212: Use minimum safe oven ventilation $3,945 $250 $3,945
21,102
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $14,372 $1,025 $14,372
76,495
kWh
- -
04 2.1233: Analyze flue gas for proper air/fuel ratio $1,350 $537 - $1,350
-
MMBtu
-
05 2.6124: Establish equipment maintenance schedule $1,596 - $1,716
9,086
kWh
- $(-120.0)
06 3.4115: Recover and reuse cooling water $700 $1,000 $(-71.0)
(-293)
kWh
- $771
07 2.2414: Use waste heat from hot flue gases to preheat $281 $2,200 - $281
-
MMBtu
-
08 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,777 $1,900 $2,777
-
kWh
- -
09 2.7224: Reduce space conditioning during non-working hours $25,374 - $14,654
77,667
kWh
$10,720
-
MMBtu
-
10 2.7494: Install storm windows and doors $14,477 $8,500 $10,886
58,030
kWh
$3,591
-
MMBtu
-
11 2.7492: Use proper thickness of insulation on building envelope $32,119 $10,000 $26,234
139,508
kWh
$5,885
-
MMBtu
-
TOTAL RECOMMENDED $104,187 $25,628 $81,709
419,989
kWh
$21,827
-
MMBtu
$651
TOTAL IMPLEMENTED $51,769 $4,678 $38,928
192,263
kWh
$12,070
-
MMBtu
$771
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #2 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs