ITAC Assessment: TT0231
ITAC logo
ITAC Assessment: TT0231
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Automotive Door Handles
NAICS 332510: Hardware Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $50
M
to 100
M
# of Employees 325
Plant Area 185,660
ft2
Annual Production 2,500,000
units
Production Hrs. Annual 6,120
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $749,451 11,252,480
kWh
Electricity Demand $319,163 26,739
kW-mo/yr
Natural Gas $91,925 22,866
MMBtu
Waste Disposal Costs
Water Usage $6,973 755
Tgal
Water Disposal $8,510 756
Tgal
TOTAL YEARLY COSTS $1,176,022
RECOMMENDED SAVINGS* $65,657 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $65,657

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $42,957 $153,710 $29,376
441,075
kWh
$13,581
-
kW-mo/yr
02 2.4225: Install common header on compressors $13,982 $1,050 $13,982
209,936
kWh
-
03 2.2511: Insulate bare equipment $4,149 $10,500 $4,149
62,297
kWh
-
04 2.6218: Turn off equipment when not in use $3,033 $25 $3,033
45,533
kWh
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $886 $40 $886
13,293
kWh
-
06 2.7212: Install or upgrade insulation on hvac distribution systems $650 $1,650 $650
9,758
kWh
-
TOTAL RECOMMENDED $65,657 $166,975 $52,076
781,892
kWh
$13,581
-
kW-mo/yr
TOTAL IMPLEMENTED $65,657 $166,975 $52,076
781,892
kWh
$13,581
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs