Assessment Year | 2019 |
---|---|
Principal Product | Smokeless Tobacco |
NAICS | 312230: Tobacco Manufacturing |
SIC | 2131: Chewing and Smoking Tobacco and Snuff |
Sales Range | $100 M to 500M |
# of Employees | 200 |
Plant Area |
787,000
ft2
|
Annual Production | 11,232
units
|
Production Hrs. Annual | 4,335
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $640,862 | 12,039,000 |
kWh
|
$0.053 | |
Electricity Demand | $363,765 | 30,041 |
kW-mo/yr
|
$12.11 | |
Natural Gas | $173,449 | 38,679 |
MMBtu
|
$4.48 | |
Waste Disposal Costs | |||||
Water Usage | $37,731 | 21,804 |
Tgal
|
$1.73 | |
Water Disposal | $54,713 | 21,803 |
Tgal
|
$2.51 | |
TOTAL YEARLY COSTS | $1,270,520 | ||||
RECOMMENDED SAVINGS* | $99,115 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $55,854 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,090 | $85,313 |
$7,793
146,484
kWh
|
$4,916
-
kW-mo/yr
|
- | - | - | $8,381 | - | |
02 | 3.4116: Meter recycled water (to reduce sewer charges) | $21,004 | $2,150 | - | - | - | - |
$21,004
-
Tgal
|
- | - | |
03 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $20,902 | $30,000 |
$20,902
392,897
kWh
|
- | - | - | - | - | - | |
04 | 2.4224: Upgrade controls on compressors | $20,301 | $8,000 |
$12,454
234,090
kWh
|
$7,847
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.2121: Increase amount of condensate returned | $5,090 | $15,000 | - | - |
$3,870
-
MMBtu
|
$1,220
-
Tgal
|
- | - | - | |
06 | 2.8114: Change rate schedules or other changes in utility service | $3,670 | $200 | - | - | - | - | - | - | $3,670 | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,000 | $2,000 | - | - |
$3,000
-
MMBtu
|
- | - | - | - | |
08 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $2,058 | $4,500 | - | - |
$2,058
-
MMBtu
|
$0
-
Tgal
|
- | - | - | |
09 | 2.2511: Insulate bare equipment | $1,202 | $2,400 | - | - |
$1,202
-
MMBtu
|
- | - | - | - | |
10 | 3.1161: Eliminate/reduce an operation | $798 | $340 |
$798
14,999
kWh
|
- | - | - | - | - | - | |
TOTAL RECOMMENDED | $99,115 | $149,903 |
$41,947
788,470
kWh
|
$12,763
-
kW-mo/yr
|
$10,130
-
MMBtu
|
$1,220
-
Tgal
|
$21,004
-
Tgal
|
$8,381 | $3,670 | ||
TOTAL IMPLEMENTED | $55,854 | $107,403 |
$8,591
161,483
kWh
|
$4,916
-
kW-mo/yr
|
$8,072
-
MMBtu
|
$1,220
-
Tgal
|
$21,004
-
Tgal
|
$8,381 | $3,670 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs