ITAC Assessment: TT0210
ITAC logo
ITAC Assessment: TT0210
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Alumina Ceramic Products
NAICS 327110: Pottery, Ceramics, and Plumbing Fixture Manufacturing
SIC 3264: Porcelain Electrical Supplies
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 125,000
ft2
Annual Production 11,544
units
Production Hrs. Annual 8,760
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $402,366 6,309,800
kWh
Electricity Demand $226,578 11,916
kW-mo/yr
Natural Gas $1,150,723 139,072
MMBtu
Waste Disposal Costs
Water Usage $15,565 2,316,000
Tgal
Water Disposal $26,583 2,316
Tgal
TOTAL YEARLY COSTS $1,821,815
RECOMMENDED SAVINGS* $24,481 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,481

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown $13,015 $9,600 $13,015
204,000
kWh
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,663 $2,000 $8,663
135,780
kWh
- -
03 2.7135: Install occupancy sensors $1,508 $3,630 $1,508
23,651
kWh
- -
04 2.7261: Install timers and/or thermostats $716 $250 $211
3,304
kWh
$505
-
MMBtu
-
05 4.812: Apply for investment incentives $579 $100 - - $579
TOTAL RECOMMENDED $24,481 $15,580 $23,397
366,735
kWh
$505
-
MMBtu
$579
TOTAL IMPLEMENTED $24,481 $15,580 $23,397
366,735
kWh
$505
-
MMBtu
$579
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs