Assessment Year | 2018 |
---|---|
Principal Product | Germanium and Charged Particle Detectors |
NAICS | 334516: Analytical Laboratory Instrument Manufacturing |
SIC | 3826: Laboratory Analytical Instruments |
Sales Range | $50 M to 100M |
# of Employees | 75 |
Plant Area |
41,000
ft2
|
Annual Production | 2,000
units
|
Production Hrs. Annual | 6,188
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $337,433 | 5,265,000 |
kWh
|
$0.064 | |
Electricity Demand | $138,788 | 9,035 |
kW-mo/yr
|
$15.36 | |
Natural Gas | $41,859 | 5,597 |
MMBtu
|
$7.48 | |
Waste Disposal Costs | |||||
Water Usage | $53,537 | 9,736,000 |
Tgal
|
$0.005 | |
Water Disposal | $59,396 | 9,736 |
Tgal
|
$6.10 | |
TOTAL YEARLY COSTS | $631,013 | ||||
RECOMMENDED SAVINGS* | $28,320 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $21,467 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,878 | $41,788 |
$12,894
201,154
kWh
|
$5,984
-
kW-mo/yr
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,922 | $9,020 |
$3,706
57,816
kWh
|
$1,216
-
kW-mo/yr
|
|
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,589 | $2,450 |
$1,915
29,879
kWh
|
$674
-
kW-mo/yr
|
|
04 | 2.2694: Use highest temperature for chilling or cold storage | $1,313 | $250 |
$1,313
20,478
kWh
|
- | |
05 | 2.4226: Use / purchase optimum sized compressor | $618 | $1,770 |
$618
9,636
kWh
|
- | |
TOTAL RECOMMENDED | $28,320 | $55,278 |
$20,446
318,963
kWh
|
$7,874
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $21,467 | $44,238 |
$14,809
231,033
kWh
|
$6,658
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs