| Assessment Year | 2017 |
|---|---|
| Principal Product | Frozen Soup |
| NAICS | 311412: Frozen Specialty Food Manufacturing |
| SIC | 2038: Frozen Specialties, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 350 |
| Plant Area |
200,000
ft2
|
| Annual Production | 90,000,000
lb
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,358,318 | 20,592,234 |
kWh
|
$0.066 | |
| Electricity Demand | $525,898 | 36,739 |
kW-mo/yr
|
$14.31 | |
| Natural Gas | $326,620 | 45,245 |
MMBtu
|
$7.22 | |
| Waste Disposal Costs | |||||
| Water Usage | $144,558 | 54,444,721 |
Tgal
|
$0.003 | |
| Water Disposal | $390,733 | 42,807 |
Tgal
|
$9.13 | |
| TOTAL YEARLY COSTS | $2,746,127 | ||||
| RECOMMENDED SAVINGS* | $32,424 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $17,365 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4224: Upgrade controls on compressors | $9,284 | $50 |
$5,711
86,528
kWh
|
$3,573
-
kW-mo/yr
|
- | |
| 02 | 2.2511: Insulate bare equipment | $7,752 | $3,175 | - | - |
$7,752
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,564 | $34,509 |
$7,312
110,796
kWh
|
$252
-
kW-mo/yr
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,495 | $3,050 |
$7,495
113,568
kWh
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $329 | $1,600 |
$329
4,992
kWh
|
- | - | |
| TOTAL RECOMMENDED | $32,424 | $42,384 |
$20,847
315,884
kWh
|
$3,825
-
kW-mo/yr
|
$7,752
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $17,365 | $4,825 |
$6,040
91,520
kWh
|
$3,573
-
kW-mo/yr
|
$7,752
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs