ITAC Assessment: TT0198
ITAC logo
ITAC Assessment: TT0198
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Frozen Soup
NAICS 311412: Frozen Specialty Food Manufacturing
SIC 2038: Frozen Specialties, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 350
Plant Area 200,000
ft2
Annual Production 90,000,000
lb
Production Hrs. Annual 4,160
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,358,318 20,592,234
kWh
Electricity Demand $525,898 36,739
kW-mo/yr
Natural Gas $326,620 45,245
MMBtu
Waste Disposal Costs
Water Usage $144,558 54,444,721
Tgal
Water Disposal $390,733 42,807
Tgal
TOTAL YEARLY COSTS $2,746,127
RECOMMENDED SAVINGS* $32,424 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,365

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4224: Upgrade controls on compressors $9,284 $50 $5,711
86,528
kWh
$3,573
-
kW-mo/yr
-
02 2.2511: Insulate bare equipment $7,752 $3,175 - - $7,752
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $7,564 $34,509 $7,312
110,796
kWh
$252
-
kW-mo/yr
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,495 $3,050 $7,495
113,568
kWh
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $329 $1,600 $329
4,992
kWh
- -
TOTAL RECOMMENDED $32,424 $42,384 $20,847
315,884
kWh
$3,825
-
kW-mo/yr
$7,752
-
MMBtu
TOTAL IMPLEMENTED $17,365 $4,825 $6,040
91,520
kWh
$3,573
-
kW-mo/yr
$7,752
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs