| Assessment Year | 2016 |
|---|---|
| Principal Product | Carbide Cutting Tools |
| NAICS | 333515: Cutting Tool and Machine Tool Accessory Manufacturing |
| SIC | 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
38,915
ft2
|
| Annual Production | 600,000
pieces
|
| Production Hrs. Annual | 4,554
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $99,859 | 1,153,343 |
kWh
|
$0.087 | |
| Electricity Demand | $13,750 | 2,625 |
kW-mo/yr
|
$5.24 | |
| Natural Gas | $3,455 | 563 |
MMBtu
|
$6.13 | |
| Waste Disposal Costs | |||||
| Water Usage | $2,094 | 320,565 |
Tgal
|
$0.007 | |
| TOTAL YEARLY COSTS | $119,158 | ||||
| RECOMMENDED SAVINGS* | $13,910 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $4,193 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,653 | $3,050 |
$6,145
70,956
kWh
|
$508
-
kW-mo/yr
|
- | - | |
| 02 | 4.812: Apply for investment incentives | $4,193 | $40 | - | - | $4,193 | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $1,598 | $530 |
$1,405
13,999
kWh
|
$193
-
kW-mo/yr
|
- | - | |
| 04 | 2.7261: Install timers and/or thermostats | $805 | $250 |
$727
8,395
kWh
|
- | - |
$78
-
MMBtu
|
|
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $332 | $125 |
$306
3,539
kWh
|
$26
-
kW-mo/yr
|
- | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $329 | $600 |
$303
3,504
kWh
|
$26
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $13,910 | $4,595 |
$8,886
100,393
kWh
|
$753
-
kW-mo/yr
|
$4,193 |
$78
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $4,193 | $40 | - | - | $4,193 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs