Assessment Year | 2016 |
---|---|
Principal Product | Headliner, blowmolded ducts, and load floor panels |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 275 |
Plant Area |
138,584
ft2
|
Annual Production | 5,195,000
pieces
|
Production Hrs. Annual | 4,125
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $985,338 | 18,448,100 |
kWh
|
$0.053 | |
Electricity Demand | $414,868 | 38,722 |
kW-mo/yr
|
$10.71 | |
Natural Gas | $31,004 | 5,031 |
MMBtu
|
$6.16 | |
Waste Disposal Costs | |||||
Water Usage | $16,478 | 4,392,000 |
Tgal
|
$0.004 | |
Water Disposal | $6,635 | 978 |
Tgal
|
$6.78 | |
TOTAL YEARLY COSTS | $1,454,323 | ||||
RECOMMENDED SAVINGS* | $121,373 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $121,373 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4224: Upgrade controls on compressors | $89,975 | $250 |
$72,479
1,367,520
kWh
|
$17,496
-
kW-mo/yr
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,541 | $46,932 |
$18,648
351,866
kWh
|
$2,893
-
kW-mo/yr
|
|
03 | 2.7122: Disconnect ballasts | $9,857 | $1,000 |
$7,373
139,104
kWh
|
$2,484
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $121,373 | $48,182 |
$98,500
1,858,490
kWh
|
$22,873
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $121,373 | $48,182 |
$98,500
1,858,490
kWh
|
$22,873
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs