Assessment Year | 2015 |
---|---|
Principal Product | Bimetallic Wire |
NAICS | 331420: Copper Rolling, Drawing, Extruding, and Alloying |
SIC | 3351: Rolling, Drawing, and Extruding Of Copper |
Sales Range | $100 M to 500M |
# of Employees | 100 |
Plant Area |
287,000
ft2
|
Annual Production | 40,000,000
lb
|
Production Hrs. Annual | 8,064
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,092,383 | 28,292,240 |
kWh
|
$0.039 |
Electricity Demand | $870,133 | 62,696 |
kW-mo/yr
|
$13.88 |
Natural Gas | $226,832 | 20,622 |
MMBtu
|
$11.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $93,208 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,826 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $31,644 | $3,000 |
$20,703
536,368
kWh
|
$10,941
-
kW-mo/yr
|
- | |
02 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $19,647 | $20,000 |
$14,651
379,560
kWh
|
$4,996
-
kW-mo/yr
|
- | |
03 | 2.7425: Clean or color roof to reduce solar load | $17,175 | $38,170 |
$7,175
185,880
kWh
|
- | $10,000 | |
04 | 2.7144: Install spectral reflectors / delamp | $8,659 | $700 |
$4,183
108,380
kWh
|
$4,476
-
kW-mo/yr
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,329 | $63 |
$3,469
89,859
kWh
|
$1,860
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,756 | $7,500 |
$3,756
97,307
kWh
|
- | - | |
07 | 2.4224: Upgrade controls on compressors | $2,995 | $1,070 |
$2,995
77,583
kWh
|
- | - | |
08 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $2,187 | $500 |
$2,187
56,646
kWh
|
- | - | |
09 | 2.4131: Size electric motors for peak operating efficiency | $1,816 | $1,000 |
$1,183
30,643
kWh
|
$633
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $93,208 | $72,003 |
$60,302
1,562,226
kWh
|
$22,906
-
kW-mo/yr
|
$10,000 | ||
TOTAL IMPLEMENTED | $36,826 | $4,570 |
$25,885
670,597
kWh
|
$10,941
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs