| Assessment Year | 2015 |
|---|---|
| Principal Product | Vinyl Windows |
| NAICS | 332321: Metal Window and Door Manufacturing |
| SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
72,323
ft2
|
| Annual Production | 16,000
pieces
|
| Production Hrs. Annual | 4,312
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $63,715 | 883,200 |
kWh
|
$0.072 |
| Electricity Demand | $30,100 | 2,856 |
kW-mo/yr
|
$10.54 |
| Natural Gas | $19,248 | 2,008 |
MMBtu
|
$9.59 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $39,612 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,176 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,474 | $54,305 |
$8,059
111,774
kWh
|
$3,415
-
kW-mo/yr
|
- | - | |
| 02 | 2.4224: Upgrade controls on compressors | $7,653 | $5,000 |
$5,432
75,334
kWh
|
$2,221
-
kW-mo/yr
|
- | - | |
| 03 | 2.8114: Change rate schedules or other changes in utility service | $7,288 | $300 | - | - | $7,288 | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,479 | $3,000 |
$5,479
75,992
kWh
|
- | - | - | |
| 05 | 4.812: Apply for investment incentives | $5,176 | $40 | - | - | - | $5,176 | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,216 | $2,000 |
$2,216
30,735
kWh
|
- | - | - | |
| 07 | 2.6218: Turn off equipment when not in use | $326 | $460 |
$326
4,521
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $39,612 | $65,105 |
$21,512
298,356
kWh
|
$5,636
-
kW-mo/yr
|
$7,288 | $5,176 | ||
| TOTAL IMPLEMENTED | $5,176 | $40 | - | - | - | $5,176 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs