Assessment Year | 2014 |
---|---|
Principal Product | Carpet |
NAICS | 314110: Carpet and Rug Mills |
SIC | 2273: Carpets and Rugs |
Sales Range | $50 M to 100M |
# of Employees | 270 |
Plant Area |
275,000
ft2
|
Annual Production | 20,508
thousand feet
|
Production Hrs. Annual | 5,460
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $379,767 | 5,905,200 |
kWh
|
$0.064 |
Electricity Demand | $184,026 | 15,218 |
kW-mo/yr
|
$12.09 |
Electricity Fees | $(-43,063.0) | - |
|
- |
Natural Gas | $327,212 | 48,002 |
MMBtu
|
$6.82 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $113,365 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $990 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $34,016 | $68,097 | - | - |
$34,016
-
MMBtu
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $73,188 | $228,000 |
$47,648
744,499
kWh
|
$25,540
-
kW-mo/yr
|
- | |
03 | 2.4225: Install common header on compressors | $5,171 | $25 |
$5,171
80,800
kWh
|
- | - | |
04 | 2.4323: Use optimum size and capacity equipment | $600 | $25 |
$477
7,446
kWh
|
$123
-
kW-mo/yr
|
- | |
05 | 2.7122: Disconnect ballasts | $390 | $130 |
$310
4,840
kWh
|
$80
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $113,365 | $296,277 |
$53,606
837,585
kWh
|
$25,743
-
kW-mo/yr
|
$34,016
-
MMBtu
|
||
TOTAL IMPLEMENTED | $990 | $155 |
$787
12,286
kWh
|
$203
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs