| Assessment Year | 2012 |
|---|---|
| Principal Product | Engineered Fiberglass Panel |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
125,000
ft2
|
| Annual Production | 48,000
thousand feet
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $191,349 | 6,714,000 |
kWh
|
$0.029 |
| Electricity Demand | $75,606 | 16,990 |
kW-mo/yr
|
$4.45 |
| Electricity Fees | $3,769 | - |
|
- |
| Natural Gas | $144,108 | 31,313 |
MMBtu
|
$4.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $58,954 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,865 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $4,085 | - |
$4,085
143,350
kWh
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $334 | - |
$334
11,700
kWh
|
- | - | |
| 03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $1,275 | $1,000 |
$1,275
44,720
kWh
|
- | - | |
| 04 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $2,764 | $2,000 |
$2,764
96,992
kWh
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $1,008 | $1,780 |
$1,008
36,000
kWh
|
- | - | |
| 06 | 2.2414: Use waste heat from hot flue gases to preheat | $29,200 | $35,000 | - | - |
$29,200
-
MMBtu
|
|
| 07 | 2.3212: Optimize plant power factor | $3,800 | $7,225 | - |
$3,800
-
kW-mo/yr
|
- | |
| 08 | 2.4151: Develop a repair/replace policy | $2,350 | $2,400 |
$2,350
82,200
kWh
|
- | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $134 | $525 |
$134
4,690
kWh
|
- | - | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,004 | $54,507 |
$14,004
491,366
kWh
|
- | - | |
| TOTAL RECOMMENDED | $58,954 | $104,437 |
$25,954
911,018
kWh
|
$3,800
-
kW-mo/yr
|
$29,200
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $7,865 | $7,705 |
$7,865
276,302
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs