| Assessment Year | 2011 |
|---|---|
| Principal Product | Valves |
| NAICS | 332912: Fluid Power Valve and Hose Fitting Manufacturing |
| SIC | 3492: Fluid Power Valves and Hose Fittings |
| Sales Range | $100 M to 500M |
| # of Employees | 330 |
| Plant Area |
290,000
ft2
|
| Annual Production | 660,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $405,359 | 14,425,488 |
kWh
|
$0.028 |
| Electricity Demand | $227,670 | 29,482 |
kW-mo/yr
|
$7.72 |
| Electricity Fees | $396,484 | - |
|
- |
| Natural Gas | $55,030 | 6,025 |
MMBtu
|
$9.13 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,186 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $900 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $339 | - |
$339
12,093
kWh
|
- | |
| 02 | 2.2113: Repair or replace steam traps | $6,712 | $4,800 |
$6,712
238,880
kWh
|
- | |
| 03 | 2.4235: Remove or close off unneeded compressed air lines | $1,238 | - |
$1,238
44,044
kWh
|
- | |
| 04 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $900 | $1,050 | - |
$900
-
Tgal
|
|
| 05 | 2.4151: Develop a repair/replace policy | $8,057 | $30,500 |
$8,057
287,000
kWh
|
- | |
| 06 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $12,516 | $4,000 |
$12,516
445,434
kWh
|
- | |
| 07 | 2.7241: Install outside air damper / economizer on hvac unit | $2,424 | $120 |
$2,424
86,283
kWh
|
- | |
| TOTAL RECOMMENDED | $32,186 | $40,470 |
$31,286
1,113,734
kWh
|
$900
-
Tgal
|
||
| TOTAL IMPLEMENTED | $900 | $1,050 | - |
$900
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs