Assessment Year | 2011 |
---|---|
Principal Product | Valves |
NAICS | 332912: Fluid Power Valve and Hose Fitting Manufacturing |
SIC | 3492: Fluid Power Valves and Hose Fittings |
Sales Range | $100 M to 500M |
# of Employees | 330 |
Plant Area |
290,000
ft2
|
Annual Production | 660,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $405,359 | 14,425,488 |
kWh
|
$0.028 |
Electricity Demand | $227,670 | 29,482 |
kW-mo/yr
|
$7.72 |
Electricity Fees | $396,484 | - |
|
- |
Natural Gas | $55,030 | 6,025 |
MMBtu
|
$9.13 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,186 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $900 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $339 | - |
$339
12,093
kWh
|
- | |
02 | 2.2113: Repair or replace steam traps | $6,712 | $4,800 |
$6,712
238,880
kWh
|
- | |
03 | 2.4235: Remove or close off unneeded compressed air lines | $1,238 | - |
$1,238
44,044
kWh
|
- | |
04 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $900 | $1,050 | - |
$900
-
Tgal
|
|
05 | 2.4151: Develop a repair/replace policy | $8,057 | $30,500 |
$8,057
287,000
kWh
|
- | |
06 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $12,516 | $4,000 |
$12,516
445,434
kWh
|
- | |
07 | 2.7241: Install outside air damper / economizer on hvac unit | $2,424 | $120 |
$2,424
86,283
kWh
|
- | |
TOTAL RECOMMENDED | $32,186 | $40,470 |
$31,286
1,113,734
kWh
|
$900
-
Tgal
|
||
TOTAL IMPLEMENTED | $900 | $1,050 | - |
$900
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs