| Assessment Year | 2010 |
|---|---|
| Principal Product | Motor Parts |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 100 |
| Plant Area |
56,000
ft2
|
| Annual Production | 17,000,000
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $71,418 | 644,400 |
kWh
|
$0.11 |
| Natural Gas | $21,216 | 2,041 |
MMBtu
|
$10.40 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $20,296 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,787 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7314: Reduce ventilation air | $5,009 | $17,120 |
$5,009
55,663
kWh
|
- | - | - | - | |
| 02 | 2.3212: Optimize plant power factor | $11,430 | $13,000 | - | - | $11,430 | - | - | |
| 03 | 3.4111: Use closed cycle process to minimize waste water production | $560 | $825 | - | - | - |
$560
-
Tgal
|
- | |
| 04 | 2.6218: Turn off equipment when not in use | $1,500 | $632 |
$1,500
16,101
kWh
|
- | - | - | - | |
| 05 | 2.4322: Use or replace with energy efficient substitutes | $520 | $15 |
$520
2,400
kWh
|
- | - | - | - | |
| 06 | 2.8121: Apply for tax-free status for energy purchases | $253 | $250 | - | - | - | - | $253 | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $1,024 | $40 |
$999
11,101
kWh
|
$25
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $20,296 | $31,882 |
$8,028
85,265
kWh
|
$25
-
kW-mo/yr
|
$11,430 |
$560
-
Tgal
|
$253 | ||
| TOTAL IMPLEMENTED | $13,787 | $14,130 |
$1,519
13,501
kWh
|
$25
-
kW-mo/yr
|
$11,430 |
$560
-
Tgal
|
$253 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs