ITAC Assessment: TT0047
ITAC logo
ITAC Assessment: TT0047
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Copper and Aluminum Wire
NAICS 331318: Other Aluminum Rolling, Drawing, and Extruding
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $50
M
to 100
M
# of Employees 73
Plant Area 150,000
ft2
Annual Production 18,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $493,956 5,954,400
kWh
Natural Gas $41,145 4,186
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,618 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7241: Install outside air damper / economizer on hvac unit $718 $800 $718
14,005
kWh
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,075 $4,900 $6,075
118,632
kWh
03 2.4235: Remove or close off unneeded compressed air lines $2,988 - $2,988
58,320
kWh
04 2.2113: Repair or replace steam traps $4,851 $1,600 $4,851
94,680
kWh
05 2.4151: Develop a repair/replace policy $986 $4,797 $986
19,243
kWh
TOTAL RECOMMENDED $15,618 $12,097 $15,618
304,880
kWh
TOTAL IMPLEMENTED - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs