ITAC Assessment: TS0002
ITAC logo
ITAC Assessment: TS0002
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product SPUN METAL PRODUCTS
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $10
M
to 50
M
# of Employees 35
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 4,000
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $24,242 260,844
kWh
Natural Gas $10,604 1,879
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,161 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,991

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6232: Install set-back timers $2,178 - $2,178
20,809
kWh
-
03 2.7492: Use proper thickness of insulation on building envelope $813 $1,310 - $813
-
MMBtu
04 2.7492: Use proper thickness of insulation on building envelope $4,170 $21,500 - $4,170
-
MMBtu
TOTAL RECOMMENDED $7,161 $22,810 $2,178
20,809
kWh
$4,983
-
MMBtu
TOTAL IMPLEMENTED $2,991 $1,310 $2,178
20,809
kWh
$813
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs