Assessment Year | 1984 |
---|---|
Principal Product | SPUN METAL PRODUCTS |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 35 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $24,242 | 260,844 |
kWh
|
$0.093 |
Natural Gas | $10,604 | 1,879 |
MMBtu
|
$5.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,161 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,991 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $2,178 | - |
$2,178
20,809
kWh
|
- | |
03 | 2.7492: Use proper thickness of insulation on building envelope | $813 | $1,310 | - |
$813
-
MMBtu
|
|
04 | 2.7492: Use proper thickness of insulation on building envelope | $4,170 | $21,500 | - |
$4,170
-
MMBtu
|
|
TOTAL RECOMMENDED | $7,161 | $22,810 |
$2,178
20,809
kWh
|
$4,983
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,991 | $1,310 |
$2,178
20,809
kWh
|
$813
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs