ITAC Assessment: TN0686
ITAC logo
ITAC Assessment: TN0686
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product kayaks
NAICS
n/a
SIC 3732: Boat Building and Repairing
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 74,000
ft2
Annual Production 14,250
pieces
Production Hrs. Annual 7,344
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,705 972,157
kWh
Electricity Demand $15,311 2,663
kW-mo/yr
Electricity Fees $2,067 -
LPG $72,028 11,225
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $82,820 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $39,000

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Product Savings
01 4.421: Modify current incentive program $30,000 $16,430 - - - - - $30,000
02 4.721: Initiate a program to acquire iso certification $24,000 $50,000 - - - - - $24,000
03 3.5315: Lease / purchase baler; sell cardboard to recycler $9,000 $5,960 - - - $9,000
-
lb
- -
04 2.2437: Recover waste heat from equipment $7,260 $18,810 - - $7,260
-
MMBtu
- - -
05 3.5311: Recover and reuse waste material $5,550 $1,120 - - - $5,550
-
lb
- -
06 2.3191: Use demand controller or load shedder $2,510 $4,780 - $2,510
-
kW-mo/yr
- - - -
07 2.7145: Install skylights $2,460 $7,100 $2,460
37,808
kWh
- - - - -
08 3.5316: Contract a wood pallet recycling company $1,280 $600 - - - $470
-
lb
$810 -
09 2.4221: Install compressor air intakes in coolest locations $760 $925 $760
11,723
kWh
- - - - -
TOTAL RECOMMENDED $82,820 $105,725 $3,220
49,531
kWh
$2,510
-
kW-mo/yr
$7,260
-
MMBtu
$15,020
-
lb
$810 $54,000
TOTAL IMPLEMENTED $39,000 $22,390 - - - $9,000
-
lb
- $30,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs