Assessment Year | 2000 |
---|---|
Principal Product | cabinet doors |
NAICS |
n/a
|
SIC | 2434: Wood Kitchen Cabinets |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
46,000
ft2
|
Annual Production | 45
thousand feet
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $54,567 | 1,573,564 |
kWh
|
$0.035 |
Electricity Demand | $15,014 | 4,080 |
kW-mo/yr
|
$3.68 |
Electricity Fees | $5,291 | - |
|
- |
Natural Gas | $6,404 | 885 |
MMBtu
|
$7.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $115,332 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $71,198 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.1191: Change procedures / equipment / operating conditions | $25,630 | $892 | - | - | - |
$25,630
-
gal
|
- | - | |
02 | 4.421: Modify current incentive program | $58,500 | $66,430 | - | - | - | - | - | $58,500 | |
03 | 3.5217: Reuse / recycle/ sell paper products | $10,570 | $640 | - | - | - | - |
$10,570
-
lb
|
- | |
04 | 2.2437: Recover waste heat from equipment | $6,404 | $1,350 | - | - |
$6,404
-
MMBtu
|
- | - | - | |
05 | 3.1161: Eliminate/reduce an operation | $6,000 | $17,000 | - | - | - | - |
$6,000
-
lb
|
- | |
06 | 2.2511: Insulate bare equipment | $3,365 | $192 |
$3,365
51,290
kWh
|
- | - | - | - | - | |
07 | 2.6218: Turn off equipment when not in use | $2,735 | $1,580 |
$2,585
74,443
kWh
|
$150
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.6232: Install set-back timers | $1,425 | $2,110 |
$307
6,448
kWh
|
- |
$1,118
-
MMBtu
|
- | - | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $506 | - |
$356
10,258
kWh
|
$150
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $197 | $352 |
$142
4,103
kWh
|
$55
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $115,332 | $90,546 |
$6,755
146,542
kWh
|
$355
-
kW-mo/yr
|
$7,522
-
MMBtu
|
$25,630
-
gal
|
$16,570
-
lb
|
$58,500 | ||
TOTAL IMPLEMENTED | $71,198 | $69,532 |
$805
20,809
kWh
|
$205
-
kW-mo/yr
|
$1,118
-
MMBtu
|
- |
$10,570
-
lb
|
$58,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs