| Assessment Year | 2000 |
|---|---|
| Principal Product | Truck Cabs |
| NAICS |
n/a
|
| SIC | 3713: Truck and Bus Bodies |
| Sales Range | $10 M to 50M |
| # of Employees | 164 |
| Plant Area |
115,000
ft2
|
| Annual Production | 13,595
pieces
|
| Production Hrs. Annual | 3,920
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $342,552 | 6,228,020 |
kWh
|
$0.055 |
| Electricity Demand | $61,017 | 18,046 |
kW-mo/yr
|
$3.38 |
| Electricity Fees | $9,318 | - |
|
- |
| Natural Gas | $166,689 | 38,717 |
MMBtu
|
$4.31 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $134,068 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $39,764 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4151: Develop a repair/replace policy | $72,335 | $1,075 |
$385
8,206
kWh
|
- | - | - | - | $71,950 | |
| 02 | 3.6112: Use filter and drying oven to reduce sludge volume | $20,125 | $25,600 | - | - | - | - |
$20,125
-
lb
|
- | |
| 03 | 4.432: Cross-train personnel to avoid lost time | $18,800 | $16,000 | - | - | - | - | - | $18,800 | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $9,789 | $16,600 |
$3,845
67,409
kWh
|
$5,944
-
MMBtu
|
- | - | - | - | |
| 05 | 3.5313: Increase amount of waste recovered for resale | $8,725 | $6,000 | - | - | - |
$8,725
-
lb
|
- | - | |
| 06 | 3.4116: Meter recycled water (to reduce sewer charges) | $2,450 | $3,300 | - | - |
$2,450
-
Tgal
|
- | - | - | |
| 07 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,844 | - |
$1,844
542,497
kWh
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $134,068 | $68,575 |
$6,074
618,112
kWh
|
$5,944
-
MMBtu
|
$2,450
-
Tgal
|
$8,725
-
lb
|
$20,125
-
lb
|
$90,750 | ||
| TOTAL IMPLEMENTED | $39,764 | $41,900 |
$3,845
67,409
kWh
|
$5,944
-
MMBtu
|
$2,450
-
Tgal
|
$8,725
-
lb
|
- | $18,800 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs