ITAC Assessment: TN0673
ITAC logo
ITAC Assessment: TN0673
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Steel doors and frames
NAICS
n/a
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $1
M
to 5
M
# of Employees 32
Plant Area 38,000
ft2
Annual Production 10,500
pieces
Production Hrs. Annual 2,800
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Demand $5,441 1,112
kW-mo/yr
Electricity Fees $3,660 -
Natural Gas $5,381 850
MMBtu
LPG $9,631 697
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,880 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,235

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings Primary Product Savings
01 2.7243: Improve air circulation with destratification fans / other methods $1,075 $2,610 - $1,075
-
MMBtu
- - -
02 4.611: Begin a practice of predictive / preventative maintenance $980 $1,075 $40
879
kWh
- - - $940
03 2.7447: Install vinyl strip / high speed / air curtain doors $715 $1,820 - $715
-
MMBtu
- - -
04 3.1191: Change procedures / equipment / operating conditions $710 - - - $710
-
lb
- -
05 3.7131: Use a rag recycle service $240 - - - $1,200
-
lb
$(-960.0) -
06 3.5316: Contract a wood pallet recycling company $160 - - - $160
-
lb
- -
TOTAL RECOMMENDED $3,880 $5,505 $40
879
kWh
$1,790
-
MMBtu
$2,070
-
lb
$(-960.0) $940
TOTAL IMPLEMENTED $1,235 $2,610 - $1,075
-
MMBtu
$160
-
lb
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs