ITAC Assessment: TN0672
ITAC logo
ITAC Assessment: TN0672
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Hermetic motors
NAICS
n/a
SIC 3621: Motors and Generators
Sales Range $50
M
to 100
M
# of Employees 400
Plant Area 200,000
ft2
Annual Production 5,000,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $796,768 19,556,565
kWh
Electricity Demand $205,980 36,492
kW-mo/yr
Electricity Fees $102,299 -
LPG $450,984 52,149
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $187,631 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Increase in Production Savings
01 4.423: Move product using mechanical means $65,150 $167,200 - - - - $58,750 $6,400
02 3.7135: Minimize use of rags through worker training $30,000 - - - - $30,000
-
lb
- -
03 2.3191: Use demand controller or load shedder $18,266 $27,000 $7,967
195,487
kWh
$10,299
-
kW-mo/yr
- - - -
04 2.2628: Utilize a less expensive cooling method $14,770 $17,800 $14,770
293,083
kWh
- - - - -
05 2.2437: Recover waste heat from equipment $13,010 $1,650 $13,010
241,794
kWh
- - - - -
06 2.7245: Use direct air supply to exhaust hoods $8,990 $19,000 $8,990
167,057
kWh
- - - - -
07 3.7214: Reduce or eliminate waste $8,100 $3,650 - - - $8,100
-
lb
- -
08 2.2437: Recover waste heat from equipment $7,385 $13,750 - - $7,385
-
MMBtu
- - -
09 2.2514: Cover open tanks $7,260 $1,500 $7,260
134,818
kWh
- - - - -
10 2.1113: Reduce combustion air flow to optimum $6,380 $13,800 $6,380
216,002
kWh
- - - - -
11 2.4314: Use synthetic lubricant $3,630 - $1,420
61,547
kWh
$2,210
-
kW-mo/yr
- - - -
12 2.4221: Install compressor air intakes in coolest locations $2,770 $1,440 $1,080
38,101
kWh
$1,690
-
kW-mo/yr
- - - -
13 2.5195: Change product design to reduce energy requirements $1,920 $5,000 $1,920
44,549
kWh
- - - - -
TOTAL RECOMMENDED $187,631 $271,790 $62,797
1,392,438
kWh
$14,199
-
kW-mo/yr
$7,385
-
MMBtu
$38,100
-
lb
$58,750 $6,400
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs