Assessment Year | 2000 |
---|---|
Principal Product | Hermetic motors |
NAICS |
n/a
|
SIC | 3621: Motors and Generators |
Sales Range | $50 M to 100M |
# of Employees | 400 |
Plant Area |
200,000
ft2
|
Annual Production | 5,000,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $796,768 | 19,556,565 |
kWh
|
$0.041 |
Electricity Demand | $205,980 | 36,492 |
kW-mo/yr
|
$5.64 |
Electricity Fees | $102,299 | - |
|
- |
LPG | $450,984 | 52,149 |
MMBtu
|
$8.65 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $187,631 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.423: Move product using mechanical means | $65,150 | $167,200 | - | - | - | - | $58,750 | $6,400 | |
02 | 3.7135: Minimize use of rags through worker training | $30,000 | - | - | - | - |
$30,000
-
lb
|
- | - | |
03 | 2.3191: Use demand controller or load shedder | $18,266 | $27,000 |
$7,967
195,487
kWh
|
$10,299
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2628: Utilize a less expensive cooling method | $14,770 | $17,800 |
$14,770
293,083
kWh
|
- | - | - | - | - | |
05 | 2.2437: Recover waste heat from equipment | $13,010 | $1,650 |
$13,010
241,794
kWh
|
- | - | - | - | - | |
06 | 2.7245: Use direct air supply to exhaust hoods | $8,990 | $19,000 |
$8,990
167,057
kWh
|
- | - | - | - | - | |
07 | 3.7214: Reduce or eliminate waste | $8,100 | $3,650 | - | - | - |
$8,100
-
lb
|
- | - | |
08 | 2.2437: Recover waste heat from equipment | $7,385 | $13,750 | - | - |
$7,385
-
MMBtu
|
- | - | - | |
09 | 2.2514: Cover open tanks | $7,260 | $1,500 |
$7,260
134,818
kWh
|
- | - | - | - | - | |
10 | 2.1113: Reduce combustion air flow to optimum | $6,380 | $13,800 |
$6,380
216,002
kWh
|
- | - | - | - | - | |
11 | 2.4314: Use synthetic lubricant | $3,630 | - |
$1,420
61,547
kWh
|
$2,210
-
kW-mo/yr
|
- | - | - | - | |
12 | 2.4221: Install compressor air intakes in coolest locations | $2,770 | $1,440 |
$1,080
38,101
kWh
|
$1,690
-
kW-mo/yr
|
- | - | - | - | |
13 | 2.5195: Change product design to reduce energy requirements | $1,920 | $5,000 |
$1,920
44,549
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $187,631 | $271,790 |
$62,797
1,392,438
kWh
|
$14,199
-
kW-mo/yr
|
$7,385
-
MMBtu
|
$38,100
-
lb
|
$58,750 | $6,400 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs