ITAC Assessment: DL0019
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Latex Paint
NAICS 325510: Paint and Coating Manufacturing
SIC 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products
Sales Range $50
M
to 100
M
# of Employees 105
Plant Area 68,000
ft2
Annual Production 4,627
Tgal
Production Hrs. Annual 6,240
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $161,162 4,060,276
kWh
Natural Gas $41,225 3,104
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $354,946 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $236,566

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings
01 2.4224: Upgrade controls on compressors $214,300 $95,000 $(-8,200.0)
(-8,200)
kWh
$240,000
-
gal
$(-17,500.0)
-
lb
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $70,880 $12,500 $70,880
581,000
kWh
- -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $22,266 $7,720 $22,266
182,512
kWh
- -
04 2.7135: Install occupancy sensors $15,891 $281 $15,891
130,253
kWh
- -
05 2.7111: Reduce illumination to minimum necessary levels $14,324 $465 $14,324
117,412
kWh
- -
06 2.4221: Install compressor air intakes in coolest locations $10,221 $2,413 $10,221
83,779
kWh
- -
07 2.4227: Use compressor air filters $3,268 $500 $3,268
26,780
kWh
- -
08 2.6212: Turn off equipment during breaks, reduce operating time $2,548 - $2,548
20,888
kWh
- -
09 2.3512: De-energize excess transformer capacity $1,248 $760 $1,248
10,227
kWh
- -
TOTAL RECOMMENDED $354,946 $119,639 $132,446
1,144,651
kWh
$240,000
-
gal
$(-17,500.0)
-
lb
TOTAL IMPLEMENTED $236,566 $102,720 $14,066
174,312
kWh
$240,000
-
gal
$(-17,500.0)
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs