| Assessment Year | 1987 |
|---|---|
| Principal Product | SILK SCREENING ON BOTTLE |
| NAICS |
n/a
|
| SIC | 2752: Commercial Printing, Lithographic |
| Sales Range | $1 M to 5M |
| # of Employees | 52 |
| Plant Area |
n/a
|
| Annual Production | 100,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $116,166 | 1,441,090 |
kWh
|
$0.081 |
| Natural Gas | $124,444 | 21,007 |
MMBtu
|
$5.92 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $25,519 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,530 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 3.4154: Eliminate leaks in water lines and valves | $4,140 | $396 | - |
$3,255
-
MMBtu
|
$885 | |
| 02 | 2.2511: Insulate bare equipment | $3,147 | $648 | - |
$3,147
-
MMBtu
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,672 | - |
$2,672
33,411
kWh
|
- | - | |
| 04 | 2.4312: Improve lubrication practices | $832 | - |
$832
10,551
kWh
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,154 | $5,600 |
$5,154
64,478
kWh
|
- | - | |
| 06 | 2.2441: Preheat boiler makeup water with waste process heat | $8,856 | $9,500 | - |
$8,856
-
MMBtu
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $718 | $1,204 |
$718
13,775
kWh
|
- | - | |
| TOTAL RECOMMENDED | $25,519 | $17,348 |
$9,376
122,215
kWh
|
$15,258
-
MMBtu
|
$885 | ||
| TOTAL IMPLEMENTED | $7,530 | $1,600 |
$3,390
47,186
kWh
|
$3,255
-
MMBtu
|
$885 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs