ITAC Assessment: GT0560
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Wood Cutting Tools
NAICS
n/a
SIC 3553: Woodworking Machinery
Sales Range $500
k
to 1
M
# of Employees 10
Plant Area 12,000
ft2
Annual Production 660
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $25,999 388,042
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,700 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,020

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,520 $4,860 $2,520
37,808
kWh
02 2.7122: Disconnect ballasts $1,240 - $1,240
10,258
kWh
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $230 $50 $230
4,982
kWh
04 2.7229: Air condition only space necessary $680 $1,000 $680
4,103
kWh
05 2.7228: Avoid introducing hot, humid, or dirty air into hvac system $2,030 $5,000 $2,030
20,809
kWh
TOTAL RECOMMENDED $6,700 $10,910 $6,700
77,960
kWh
TOTAL IMPLEMENTED $6,020 $9,910 $6,020
73,857
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs