Assessment Year | 1999 |
---|---|
Principal Product | Candy |
NAICS |
n/a
|
SIC | 2064: Candy and Other Confectionery Products |
Sales Range | $5 M to 10M |
# of Employees | 90 |
Plant Area |
78,000
ft2
|
Annual Production | 7,000,000
lb
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $66,688 | 1,726,260 |
kWh
|
$0.039 |
Electricity Demand | $49,592 | 4,133 |
kW-mo/yr
|
$12.00 |
Electricity Fees | $7,416 | - |
|
- |
LPG | $67,613 | 12,270 |
MMBtu
|
$5.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $460,195 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Primary Product Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.652: Replace existing equipment with more suitable substitutes | $250,000 | $2,030 | - | - | - | - | - | $250,000 | - | |
02 | 4.445: Install equipment to move product | $108,400 | $34,670 | - | - | - | - | - | $108,400 | - | |
03 | 4.421: Modify current incentive program | $45,000 | $16,375 | - | - | - | - | $45,000 | - | - | |
04 | 2.4157: Establish a predictive maintenance program | $28,195 | $1,075 |
$70
2,052
kWh
|
- | - | - | - | $28,125 | - | |
05 | 3.5317: Sell / offer by-product as animal feed | $21,560 | - | - | - | - | - | - | - | $21,560 | |
06 | 2.3212: Optimize plant power factor | $4,000 | $13,000 | - | - | $4,000 | - | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,680 | $11,780 |
$1,120
33,998
kWh
|
$1,560
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.2136: Install / repair insulation on steam lines | $360 | $305 | - | - | - |
$360
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $460,195 | $79,235 |
$1,190
36,050
kWh
|
$1,560
-
kW-mo/yr
|
$4,000 |
$360
-
MMBtu
|
$45,000 | $386,525 | $21,560 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Primary Product Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs