Assessment Year | 1999 |
---|---|
Principal Product | Houseboats |
NAICS |
n/a
|
SIC | 3732: Boat Building and Repairing |
Sales Range | $10 M to 50M |
# of Employees | 245 |
Plant Area |
137,000
ft2
|
Annual Production | 100
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $14,951 | 443,142 |
kWh
|
$0.034 |
Electricity Demand | $10,391 | 1,732 |
kW-mo/yr
|
$6.00 |
Electricity Fees | $1,363 | - |
|
- |
LPG | $3,177 | 426 |
MMBtu
|
$7.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $62,035 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.421: Modify current incentive program | $18,750 | $30,000 | n/a | - | - | - | - | $18,750 |
02 | 3.5311: Recover and reuse waste material | $13,460 | $2,860 | n/a | - | - | - |
$13,460
-
lb
|
- |
03 | 3.5311: Recover and reuse waste material | $11,520 | $6,670 | n/a | - | - | - |
$11,520
-
lb
|
- |
04 | 3.5217: Reuse / recycle/ sell paper products | $6,880 | $480 | n/a | - | - | - |
$6,880
-
lb
|
- |
05 | 2.5113: Use direct flame impingement or infrared processing for chamber type heating | $6,106 | $14,800 | n/a | - | - |
$6,106
-
MMBtu
|
- | - |
06 | 2.7243: Improve air circulation with destratification fans / other methods | $2,870 | $3,144 | n/a | - | - |
$2,870
-
MMBtu
|
- | - |
07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,005 | $2,500 | n/a | - | - |
$1,005
-
MMBtu
|
- | - |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $565 | - | n/a |
$349
10,258
kWh
|
$216
-
kW-mo/yr
|
- | - | - |
09 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $520 | - | n/a | - | - | - |
$520
-
lb
|
- |
10 | 2.6212: Turn off equipment during breaks, reduce operating time | $359 | - | n/a |
$359
10,551
kWh
|
- | - | - | - |
TOTAL RECOMMENDED | $62,035 | $60,454 |
$708
20,809
kWh
|
$216
-
kW-mo/yr
|
$9,981
-
MMBtu
|
$32,380
-
lb
|
$18,750 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs