| Assessment Year | 2000 |
|---|---|
| Principal Product | Snack Foods |
| NAICS |
n/a
|
| SIC | 2096: Potato Chips, Corn Chips, and Similar Snacks |
| Sales Range | $50 M to 100M |
| # of Employees | 250 |
| Plant Area |
40,000
ft2
|
| Annual Production | 6,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $536,774 | 16,403,576 |
kWh
|
$0.033 |
| Electricity Demand | $316,557 | 33,688 |
kW-mo/yr
|
$9.40 |
| Electricity Fees | $(-20,686.0) | - |
|
- |
| Natural Gas | $335,668 | 90,410 |
MMBtu
|
$3.71 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $229,555 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,550 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.421: Modify current incentive program | $150,000 | $30,000 | - | - | - | - | - | $(-60,000.0) | - | - | $210,000 | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,400 | - |
$5,100
150,059
kWh
|
$3,300
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
| 03 | 3.1191: Change procedures / equipment / operating conditions | $8,150 | - | - | - | - | - |
$150
-
gal
|
- | - | $8,000 | - | |
| 04 | 2.2511: Insulate bare equipment | $6,220 | $2,180 |
$6,220
122,509
kWh
|
- | - | - | - | - | - | - | - | |
| 05 | 2.2441: Preheat boiler makeup water with waste process heat | $6,350 | $36,000 | - | - |
$6,350
-
MMBtu
|
- | - | - | - | - | - | |
| 06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,960 | $16,600 | - | - | - | - | - | - | $3,960 | - | - | |
| 07 | 3.4111: Use closed cycle process to minimize waste water production | $39,640 | $30,500 |
$2,010
(-59,203)
kWh
|
$1,025
-
kW-mo/yr
|
- |
$36,605
-
Tgal
|
- | - | - | - | - | |
| 08 | 2.2163: Use minimum steam operating pressure | $5,280 | - | - | - |
$5,280
-
MMBtu
|
- | - | - | - | - | - | |
| 09 | 2.4221: Install compressor air intakes in coolest locations | $1,555 | $1,120 |
$175
56,858
kWh
|
$1,380
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
| TOTAL RECOMMENDED | $229,555 | $116,400 |
$13,505
270,223
kWh
|
$5,705
-
kW-mo/yr
|
$11,630
-
MMBtu
|
$36,605
-
Tgal
|
$150
-
gal
|
$(-60,000.0) | $3,960 | $8,000 | $210,000 | ||
| TOTAL IMPLEMENTED | $16,550 | - |
$5,100
150,059
kWh
|
$3,300
-
kW-mo/yr
|
- | - |
$150
-
gal
|
- | - | $8,000 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs