ITAC Assessment: TN0649
ITAC logo
ITAC Assessment: TN0649
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Finished apparel
NAICS
n/a
SIC 2261: Finishers of Broadwoven Fabrics of Cotton
Sales Range $10
M
to 50
M
# of Employees 361
Plant Area 40,000
ft2
Annual Production 6,000,000
pieces
Production Hrs. Annual 4,250
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $63,070 1,483,001
kWh
Electricity Demand $36,013 4,438
kW-mo/yr
Electricity Fees $2,970 -
Natural Gas $125,746 28,212
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,555 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Personnel Changes Savings Primary Product Savings
01 4.421: Modify current incentive program $15,000 $16,370 - - - - - $(-150,000.0) $165,000
02 3.7311: Maintain machines to reduce leaks $9,350 $6,920 - - - $340
-
Tgal
$9,010
-
gal
- -
03 3.5311: Recover and reuse waste material $8,380 $15,300 - - $8,380
-
MMBtu
- - - -
04 2.2113: Repair or replace steam traps $5,140 - - - $5,890
-
MMBtu
- - $(-750.0) -
05 2.7111: Reduce illumination to minimum necessary levels $4,500 $2,830 $2,950
84,115
kWh
$1,550
-
kW-mo/yr
- - - - -
06 2.2135: Repair and eliminate steam leaks $2,185 $100 - - $2,185
-
MMBtu
- - - -
TOTAL RECOMMENDED $44,555 $41,520 $2,950
84,115
kWh
$1,550
-
kW-mo/yr
$16,455
-
MMBtu
$340
-
Tgal
$9,010
-
gal
$(-150,750.0) $165,000
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Personnel Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs