ITAC Assessment: TN0645
ITAC logo
ITAC Assessment: TN0645
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Internal combustion engine bearings
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $50
M
to 100
M
# of Employees 615
Plant Area 266,000
ft2
Annual Production 100,000,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $588,250 28,555,100
kWh
Electricity Demand $519,065 37,296
kW-mo/yr
Electricity Fees $424,019 -
Natural Gas $323,547 61,916
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,513,070 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $424,900

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Primary Product Savings By-product Production Savings
01 3.1242: Allow drainage before withdrawing object $408,630 $24,685 - - - $239,950
-
Tgal
$46,250
-
lb
- $122,430 - -
02 3.4112: Recovery metals from rinse water(evap., ion exchange, ro, electrolysis, electrodialysis) and reuse rinse water $277,345 $644,800 - - - $275,890
-
Tgal
$61,455
-
lb
$(-60,000.0) - - -
03 3.1244: Reduce solution drag-out to prevent solution loss $237,600 $153,485 - - - $119,975
-
Tgal
$23,125
-
lb
$(-28,000.0) $122,500 - -
04 3.5248: Separate and recycle scrap metal to foundry or for sale $221,455 $70,000 - - $(-34,140.0)
-
MMBtu
- - $(-422,220.0) - - $677,815
05 4.721: Initiate a program to acquire iso certification $198,225 $250,000 - - - - - - - $198,225 -
06 3.1175: Use a different or recycled raw material $51,945 $200,000 - - - $101,945
-
Tgal
- $(-50,000.0) - - -
07 3.4132: Use deionized water in upstream rinse tanks $48,650 $120,000 - - - - $68,150
-
lb
$(-19,500.0) - - -
08 3.4113: Treat and reuse rinse waters $28,105 $69,200 - - - $28,105
-
Tgal
- - - - -
09 2.6232: Install set-back timers $15,755 $1,555 $15,755
395,662
kWh
- - - - - - - -
10 3.4154: Eliminate leaks in water lines and valves $9,390 $8,000 - - - $9,390
-
Tgal
- - - - -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,880 $5,000 $6,680
317,995
kWh
$200
-
kW-mo/yr
- - - - - - -
12 2.4221: Install compressor air intakes in coolest locations $6,310 $1,120 $6,060
288,687
kWh
$250
-
kW-mo/yr
- - - - - - -
13 2.2441: Preheat boiler makeup water with waste process heat $2,780 $14,300 - - $2,780
-
MMBtu
- - - - - -
TOTAL RECOMMENDED $1,513,070 $1,562,145 $28,495
1,002,344
kWh
$450
-
kW-mo/yr
$(-31,360.0)
-
MMBtu
$775,255
-
Tgal
$198,980
-
lb
$(-579,720.0) $244,930 $198,225 $677,815
TOTAL IMPLEMENTED $424,900 $37,685 $6,680
317,995
kWh
$200
-
kW-mo/yr
- $249,340
-
Tgal
$46,250
-
lb
- $122,430 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Primary Product Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs